Project Description
This project includes multiple elements to improve safety and mobility at the US 29 and Hydraulic Road intersection and nearby intersections and interchanges. It includes eliminating left turning movements from Hydraulic Road onto US 29, facilitating safe pedestrian access across 29 at the intersection, creating a Continuous Green T intersection at Angus Road, constructing a bike/ped bridge across US 29 at Zan Road, and replacing the signalized intersection at Hillsdale Drive and Hydraulic Drive with a roundabout.
Needs Addressed
Safety
Congestion
Pedestrian Access
Bicycle Access
Economic Development
Cost Estimate
Preliminary Engineering ………………………………$2.0 million
Right of Way Acquisition ………………………………$2.4 million
Construction ………………………………………$20.2 million
Outstanding Concerns
No known concerns at this time
Entity Submitting
Charlottesville/Albemarle MPO